Construction Update From the Building Committee
A new storage container has been ordered and delivered. This container will be utilized to move the office furniture into. This will allow the offices to be updated with new flooring, ceiling and lighting. The existing restroom will also be updated to match the new northside restrooms. The offices will be cleared out by 1/26. Work will begin on 1/27
The old duct work has been removed. Saw cutting for the new duct work will begin on 1/27. The arched stained glass window openings will also be cut during this process.The electrician will fix the north parking lot lights next week. He will also trench for the power to the two new monument stub walls. The framing for the 3rd floor of the bell tower will be completed next week allowing for the decking and the ladders to be installed.
We are still on schedule for a Q3 completion.
This week's photos
all of the large beams have been installed
the future cry room metal studs have been installed
getting ready to install the roof above the transepts and Sanctuary